The Building Follow-Up

- March 27th, 2010 -

One week ago, we saw 70 - 80% of our building come up in a mere 5 days.
We had the frame all up, basic siding, and about 3/4 of the roof decked and covered with felt.

This week, we were able to hire a team of workers to come out. This is what they did:
1. They finished covering the whole roof
2. They put shingles on the entire roof
3. They progressed in their work on the various roof porches



|